Data Centre Construction Cost Guide Data Centre Construction Cost Guide

Asia Pacific Data Centre Construction Cost Guide 2023/24

Access the guide

Asia Pacific is attractive to investors for its comparatively low land and development costs and for the growth potential in both developed and emerging markets. 
Regional Land Cost Index - Top 5 Markets
An increasing scarcity of suitable land parcels with available power in some markets, combined with higher borrowing costs in most markets, have contributed to cost increases. The top 5 most expensive markets for land cost are:

Regional Construction Cost Index - Top 5 Markets
With year-on-year increases of between 8% in Singapore and 3.5% in Australia, the top 5 most expensive markets for construction cost are:
 


Although supply chain disruption and supply/demand imbalances for both labour and materials remain in recovery, raw material prices, energy and transport costs remain at an all-time high and continue to contribute towards record construction costs. Overall, the market has seen an average increase of 4.9% on 2022 construction pricing.

ASIA PACIFIC DATA CENTRE CONSTRUCTION COST GUIDE 2023/24

Cushman & Wakefield’s inaugural Data Centre Construction Cost Guide 2023/24 provides a comprehensive analysis of both land purchase and data centre construction costs across Asia Pacific, as well as a schedule of land banking rates and a summary of key trends within the sector.
ACCESS THE GUIDE External Link

CONTACTS

Data-Center-Update_EMEA_web-card-q32022
Research

EMEA Data Centre Market Update

EMEA now totals to a massive 7.6GW of operational IT data centre capacity, a 10% rise from H1 2023. In addition, the region has 2.3GW capacity under construction and 6.6GW in planned stages. 
Andrew Fray • 5/2/2024
2024 Global Data Center Market Comparison Report
Research

Global Data Center Market Comparison

Explore a unique way to assess and score 92 global primary and emerging data center markets utilizing 14 criteria.
3/26/2024
Data Centre Construction Cost Guide
Insights • Technology

Asia Pacific Data Centre Construction Cost Guide 2023/24

Cushman & Wakefield's Data Centre Construction Cost Guide 2023/24 provides a comprehensive analysis of both land purchase and data centre construction costs across Asia Pacific, as well as a summary of key trends observed within the sector.
Vivek Dahiya • 10/31/2023
Colocation
Insights

Why go COLO?

Migrating to a colocation (colo) data centre can help with long term costs savings, ensure 24/7 reliability with minimal power interruptions, achieve higher sustainability and flexibility in line with your business goals.
Vivek Dahiya • 5/25/2023
Trinity
Research

A new trinity for measuring data centre sustainability

Explore how Power Usage Efficiency (PUE), in combination with Water Usage Efficiency (WUE) and Carbon Usage Effectiveness (CUE) can form a more holistic measure of sustainability performance for data centres.
Vivek Dahiya • 9/12/2022
Data Centers
Insights

2022 Global Data Center Market Comparison

Explore a unique way to assess and score 55 global primary and emerging data center markets utilizing 13 criteria.
2/22/2022
James Normandale
James Normandale

Alternative Assets Lead, Project & Development Services, Asia Pacific
Singapore


VCard downloaden

Vivek Dahiya
Vivek Dahiya

Managing Director & Head - Data Centre Advisory Team, Asia Pacific
Gurgaon, India


VCard downloaden

Christine_Ho_640x640
Christine Ho

Associate Director, Client Services
Singapore, Singapore


VCard downloaden

Dominic-Brown_Headshot_AP
Dominic Brown

Head of International Research, Global Think Tank
Brisbane, Australia


VCard downloaden

Rebecca Jung
Rebecca Jung

Associate Director, Business Development ServicesAssociate Director, Business Development Services
Sydney, Australia


VCard downloaden

Related articles

Data-Center-Update_EMEA_web-card-q32022
Research

EMEA Data Centre Market Update

EMEA now totals to a massive 7.6GW of operational IT data centre capacity, a 10% rise from H1 2023. In addition, the region has 2.3GW capacity under construction and 6.6GW in planned stages. 
Andrew Fray • 5/2/2024
2024 Global Data Center Market Comparison Report
Research

Global Data Center Market Comparison

Explore a unique way to assess and score 92 global primary and emerging data center markets utilizing 14 criteria.
3/26/2024
Hotel Construction
Data centre construction cost increases of up to 8% across region year-over-year but development shows no sign of pausing

Japan has been named the most expensive market for data centre construction while Singapore has topped the rankings for the most expensive land costs in Asia Pacific, according to a new report.

Amy Kathleen Kelly • 11/6/2023

Data Centre Construction Cost Guide
Insights • Technology

Asia Pacific Data Centre Construction Cost Guide 2023/24

Cushman & Wakefield's Data Centre Construction Cost Guide 2023/24 provides a comprehensive analysis of both land purchase and data centre construction costs across Asia Pacific, as well as a summary of key trends observed within the sector.
Vivek Dahiya • 10/31/2023
Colocation
Insights

Why go COLO?

Migrating to a colocation (colo) data centre can help with long term costs savings, ensure 24/7 reliability with minimal power interruptions, achieve higher sustainability and flexibility in line with your business goals.
Vivek Dahiya • 5/25/2023
Trinity
Research

A new trinity for measuring data centre sustainability

Explore how Power Usage Efficiency (PUE), in combination with Water Usage Efficiency (WUE) and Carbon Usage Effectiveness (CUE) can form a more holistic measure of sustainability performance for data centres.
Vivek Dahiya • 9/12/2022
Data Centre India webinar
Insights

Data Centres | The future of Colocation

Organizations across the world are evolving their flexible work environments by moving their workloads into a mix of on-premises, colocation setups, public cloud, or private cloud solutions. 
Vivek Dahiya • 8/16/2022
Data Centers
Insights

2022 Global Data Center Market Comparison

Explore a unique way to assess and score 55 global primary and emerging data center markets utilizing 13 criteria.
2/22/2022
Insights

$name

Insights

$name

$name

Cushman & Wakefield gebruikt cookies om internetverkeer te analyseren en onze klanten de beste ervaring op deze website te bieden. Sluit het venster om uw toestemming te bevestigen, of ga naar deze pagina voor meer informatie:
Cookie Notice

MORE OPTIONS
Akkoord en sluiten
These cookies ensure that our website performs as expected,for example website traffic load is balanced across our servers to prevent our website from crashing during particularly high usage.
These cookies allow our website to remember choices you make (such as your user name, language or the region you are in) and provide enhanced features. These cookies do not gather any information about you that could be used for advertising or remember where you have been on the internet.
These cookies allow us to work with our marketing partners to understand which ads or links you have clicked on before arriving on our website or to help us make our advertising more relevant to you.
Agree All
Reject All
SAVE SETTINGS